Wensleydale Railway - Photo Archive


September 2015
Photographs
This month we have:-
1. The Leyburn Working Party's Container replacement
2. The infrastructure Team at Constable Burton
3. Test drilling for the new shed at Leeming Bar
4. The Direct Works Team at Leeming Bar
Also a report of work carried out on the meeting/cafe coach at Aysgarth Station can be seen here.
This report should have gone into Relay 71, but there was not room for it.

Ref - 339
Photo - Michael Metcalfe
This 40ft container was the base for the Leyburn Work Party for 7 years before the land under it was sold by NR to a developer. The Container was cut up and loaded onto the truck in sections. (10/09/2015)
Click here to see higher resolution photo
Ref - 339
Photo - Michael Metcalfe
This 40ft container was the base for the Leyburn Work Party for 7 years before the land under it was sold by NR to a developer. The Container was cut up and loaded onto the truck in sections. (10/09/2015)
Click here to see higher resolution photo
Ref - 340
Photo - Michael Metcalfe
This 40ft container was the base for the Leyburn Work Party for 7 years before the land under it was sold by NR to a developer. The Container was cut up and loaded onto the truck in sections. (11/09/2015)
Click here to see higher resolution photo
Ref - 341
Photo - Michael Metcalfe
The new 20ft container for the Leyburn Working Party - during a tea break on the changeover day (09/09/2015)
Click here to see higher resolution photo
Ref - 342
Photo - John Thompson
The Infrastructure Team replacing 12ft point sleepers at Constable Burton (19/09/2015)
Click here to see higher resolution photo
Ref - 343
Photo - John Thompson
The Infrastructure Team disposing of vegetation at Constable Burton (19/09/2015)
Click here to see higher resolution photo
Ref - 344
Photo - John Tong
A commercial company did the 1st test borings in the LBR yard to look at the suitability for building our new Locomotive/Carriage shed (30/09/2015)
Click here to see higher resolution photo
Ref - 345
Photo - John Tong
A commercial company did the 1st test borings in the LBR yard to look at the suitability for building our new Locomotive/Carriage shed (31/09/2015)
Click here to see higher resolution photo
Ref - 346
Photo - John Tong
The Direct Works Team putting concrete foundations for concrete blocks at the west end of Leeming Bar Station. (09/09/2015)
Click here to see higher resolution photo
Ref - 347
Photo - John Tong
The Direct Works Team putting concrete foundations for concrete blocks at the west end of Leeming Bar Station. (09/09/2015)
Click here to see higher resolution photo
Ref - 348
Photo - John Tong
The Direct Works Team mixing the concrete for the concrete foundations at Leeming Bar station (09/09/2015)
Click here to see higher resolution photo
Ref - 349
Photo - John Tong
The Direct Works Team mixing the concrete for the concrete foundations at Leeming Bar station (09/09/2015)
Click here to see higher resolution photo
Ref - 350
Photo - John Tong
The Direct Works Team pouring the concrete for the concrete foundations at Leeming Bar station (09/09/2015)
Click here to see higher resolution photo
Ref - 351
Photo - John Tong
The Direct Works Team levelling the concrete for the concrete foundations at Leeming Bar station (09/09/2015)
Click here to see higher resolution photo
Ref - 352
Photo - John Tong
The new concrete foundations at the west end of Leeming Bar platform complete (09/09/2015)
Click here to see higher resolution photo
Ref - 353
Photo - John Tong
The Direct Works Team repainting Leeming Bar Signal Box (09/09/2015)
Click here to see higher resolution photo
Ref - 354
Photo - John Tong
The Direct Works Team repainting Leeming Bar Signal Box (09/09/2015)
Click here to see higher resolution photo
Ref - 355
Photo - John Tong
The Direct Works Team doing some maintenance on the picnic table on Leeming Bar platform (09/09/2015)
Click here to see higher resolution photo
Ref - 9007
Photo - John Tong
The Direct Works Team working on a concrete block wall at the end of Leeming Bar platform (23/09/2015)
Click here to see higher resolution photo
Ref - 9008
Photo - John Tong
The Direct Works Team working on a concrete block wall at the end of Leeming Bar platform (23/09/2015)
Click here to see higher resolution photo
Ref - 9009
Photo - John Tong
The Direct Works Team cutting some concrete blocks for the wall at the end of Leeming Bar platform (23/09/2015)
Click here to see higher resolution photo