Wensleydale Railway - Photo Archive


Infrastructure Work - January 2021
This January the Infrastructure Department undertook a whole month of engineering works led by Toby Lampitt our Infrastructure Supervisor supported by Alex Lomas the railways own apprentice plus volunteers from both Leyburn & Leeming Infrastructure teams . A 14 tonne tracked machine plus skilled driver/operator Eddie was hired in plus a large Tele Handler for the lifting jobs. The following works were carried out:-
1. Track renewal at Argill Farm. This added eight 60ft track panels to the eleven that the Army replaced last October.
2. Replacement of Smiths User Works Crossing. Due to the bad drainage conditions in this area, a whole section of track had to be removed and the trackbed completely replaced with new drainage installed. A new section of track was installed and a new crossing surface provided.

Ref - 6632
Photo - Alex Lomax
Argil Track Renewal - Although the first working week of 2021 isn't what any of us had hoped for here are a couple of images from the works train heading to Argill farm where some finishing off work needs completing following October's exercise. (04/01/2021)
Click here to see higher resolution photo
Ref - 6632
Photo - Alex Lomax
Argil Track Renewal - Although the first working week of 2021 isn't what any of us had hoped for here are a couple of images from the works train heading to Argill farm where some finishing off work needs completing following October's exercise. (04/01/2021)
Click here to see higher resolution photo
Ref - 6560
Photo - Alex Lomax
Argil Track Renewal - Although the first working week of 2021 isn't what any of us had hoped for here are a couple of images from the works train heading to Argill farm where some finishing off work needs completing following October's exercise. (04/01/2021)
Click here to see higher resolution photo
Ref - 6599
Photo - Michael Metcalfe
Argil Track Renewal - Works train arrived at Leyburn Peter Blacks UWC for loading of the excavator for transit to the Argill worksite. (04/01/2021)
Click here to see higher resolution photo
Ref - 6559
Photo - Michael Metcalfe
Argil Track Renewal - The railways mini digger was brought to Leyburn alongside 20166. (04/01/2021)
Click here to see higher resolution photo
Ref - 6600
Photo - Michael Metcalfe
Argil Track Renewal - The excavator was unloaded at Argill Farm UWC - space was tight. (04/01/2021)
Click here to see higher resolution photo
Ref - 6561
Photo - Michael Metcalfe
Argil Track Renewal - Concrete sleepers been loaded at Leyburn. (05/01/2021)
Click here to see higher resolution photo
Ref - 6562
Photo - Michael Metcalfe
Argil Track Renewal - Salmon now loaded with concrete sleepers at Leyburn and to be taken to Argill for unloading. (05/01/2021)
Click here to see higher resolution photo
Ref - 6633
Photo - Alex Lomax
Argil Track Renewal - Class 20 heading a works train transporting transporting the concrete sleepers the track relaying work at Argill farm, to continue on from what the Army did last year. (05/01/2021)
Click here to see higher resolution photo
Ref - 6563
Photo - Alex Lomax
Argil Track Renewal - Equipment being loaded onto a works train for the track relaying work at Argill farm, to continue on from what the Army did last year. (05/01/2021)
Click here to see higher resolution photo
Ref - 6564
Photo - Alex Lomax
Argil Track Renewal - Class 20 heading a works train over Wensley crossing. (05/01/2021)
Click here to see higher resolution photo
Ref - 6565
Photo - Alex Lomax
Argil Track Renewal - Class 20 heading a works train transporting transporting the concrete sleepers the track relaying work at Argill farm, to continue on from what the Army did last year. (05/01/2021)
Click here to see higher resolution photo
Ref - 6566
Photo - Michael Metcalfe
Argil Track Renewal - 20166 back at Leyburn for more sleeper loading. (06/01/2021)
Click here to see higher resolution photo
Ref - 6567
Photo - Michael Metcalfe
Argil Track Renewal - A pallet load of fittings been loaded on top of the sleepers. (06/01/2021)
Click here to see higher resolution photo
Ref - 6601
Photo - Michael Metcalfe
Argil Track Renewal - Sleepers are unloaded and stacked up at the Argill worksite. (06/01/2021)
Click here to see higher resolution photo
Ref - 6568
Photo - Michael Metcalfe
Argil Track Renewal - Once all materials were on site and works train wagons left at Leyburn, 20166 and Shark Van head back to Leeming Bar. (06/01/2021)
Click here to see higher resolution photo
Ref - 6602
Photo - Michael Metcalfe
Argil Track Renewal - Rail been removed by the excavator. (06/01/2021)
Click here to see higher resolution photo
Ref - 6569
Photo - Michael Metcalfe
Argil Track Renewal - The Flat bottom rail which was supplied by Network Rail was brand new and so new fishplate holes needed drilling by a team of two. (07/01/2021)
Click here to see higher resolution photo
Ref - 6622
Photo - Andy Glendinning
Argil Track Renewal - Argill Farm looking east. Recovering old rail from down the bank at the end of the Army relay. (07/01/2021)
Click here to see higher resolution photo
Ref - 6570
Photo - Andy Waite
Argil Track Renewal - The infrastructure team working on the track relaying at Argill farm (11/01/2021)
Click here to see higher resolution photo
Ref - 6623
Photo - Andy Glendinning
Argil Track Renewal - Argill Farm looking west.New track in place. (12/01/2021)
Click here to see higher resolution photo
Ref - 6573
Photo - Andy Glendinning
Argil Track Renewal - Argill Farm. Drilling fishplate bolt holes in the recently cut existing rail to put in the closure rails to connect with the new track. (13/01/2021)
Click here to see higher resolution photo
Ref - 6571
Photo - Michael Metcalfe
Argil Track Renewal - With all sleepers and rails in, this is the view back towards Leyburn where a couple of closure rails will be still be needed. (13/01/2021)
Click here to see higher resolution photo
Ref - 6572
Photo - Michael Metcalfe
Argil Track Renewal - 8 x 60' panels were laid adding onto the 11 that the Army did. (13/01/2021)
Click here to see higher resolution photo
Ref - 6603
Photo - Michael Metcalfe
Argil Track Renewal - A few bad dips and alignment tweaks were Robel packed on the Army laid section. (13/01/2021)
Click here to see higher resolution photo
Ref - 6625
Photo - Andy Glendinning
Argil Track Renewal - The works train arrives at Leyburn. (14/01/2021)
Click here to see higher resolution photo
Ref - 6578
Photo - Andy Glendinning
Argil Track Renewal - Shunting at Leyburn to form up the works train with the Flatrol and Salmon. (14/01/2021)
Click here to see higher resolution photo
Ref - 6574
Photo - Michael Metcalfe
Argil Track Renewal - Winter has arrived and 20166 is back at Leyburn to load ballast. (14/01/2021)
Click here to see higher resolution photo
Ref - 6575
Photo - Michael Metcalfe
Argil Track Renewal - The JCB loader getting stuck into the ballast heap which was also supplied by Network Rail. (14/01/2021)
Click here to see higher resolution photo
Ref - 6604
Photo - Michael Metcalfe
Argil Track Renewal - The Seacow ballast hopper being loaded. (14/01/2021)
Click here to see higher resolution photo
Ref - 6576
Photo - Michael Metcalfe
Argil Track Renewal - A decent height closure rail was loaded onto the Salmon. (14/01/2021)
Click here to see higher resolution photo
Ref - 6579
Photo - Andy Glendinning
Argil Track Renewal - Passing Wensley Crossing heading to Redmire. (14/01/2021)
Click here to see higher resolution photo
Ref - 6577
Photo - Michael Metcalfe
Argil Track Renewal - 20166 is now at Redmire to collect the Dogfish ballast wagons. (14/01/2021)
Click here to see higher resolution photo
Ref - 6580
Photo - Andy Glendinning
Argil Track Renewal - Recovering the Dogfish from Redmire sidings. (14/01/2021)
Click here to see higher resolution photo
Ref - 6581
Photo - Andy Waite
Argil Track Renewal - The works train whilst track relaying at Argill farm (14/01/2021)
Click here to see higher resolution photo
Ref - 6631
Photo - Andy Waite
Argil Track Renewal - The works train whilst track relaying at Argill farm (14/01/2021)
Click here to see higher resolution photo
Ref - 6586
Photo - Andy Glendinning
Argil Track Renewal - The difference a day makes. Almost warm loading ballast into the Dogfish. (15/01/2021)
Click here to see higher resolution photo
Ref - 6582
Photo - Michael Metcalfe
Argil Track Renewal - A Dogfish ballast wagon been loaded and all the available ballast is now in the ballast wagons. Due to the snow the ballast has not been dropped at Argill yet. (15/01/2021)
Click here to see higher resolution photo
Ref - 6583
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - Andy G getting more than his fair share of daily exercise removing 4 inch of snow off the Salmon.
I did the Flatrol wagon I'm standing on.! (15/01/2021)Click here to see higher resolution photo
Ref - 6605
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - Concrete sleepers for Smiths UWC deck replacement being lifted at Leyburn. These had been earmarked for Smiths for a while now. (15/01/2021)
Click here to see higher resolution photo
Ref - 6584
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - Sleepers been loaded onto the Salmon. (15/01/2021)
Click here to see higher resolution photo
Ref - 6585
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - Extra digging buckets for the excavator been loaded. (15/01/2021)
Click here to see higher resolution photo
Ref - 6587
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - Smiths UWC renewal starts by cleaning out drainage ditches. The crossing lies between the demolished Constable Burton Station and Finghall Station and is used by Constable Burton Estates vehicular traffic mainly. (18/01/2021)
Click here to see higher resolution photo
Ref - 6606
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - These concrete U tubes were under the crossing and fully blocked with silt from water/soil from the road to the right which is uphill. These tubes have been laid on a bed of ballast and will be covered by old upturned concrete sleepers. (18/01/2021)
Click here to see higher resolution photo
Ref - 6626
Photo - Andy Glendinning
Smiths User Worked Crossing Replacement - Drainage work at Smiths User Worked Crossing. (18/01/2021)
Click here to see higher resolution photo
Ref - 6588
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - Drainage meeting points with a vertical inspection tube installed. (21/01/2021)
Click here to see higher resolution photo
Ref - 6607
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - Trackbed dug out ready for replacement. (21/01/2021)
Click here to see higher resolution photo
Ref - 6589
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - Ballast been dumped into the void. (21/01/2021)
Click here to see higher resolution photo
Ref - 6608
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - A good wackering taking place. (22/01/2021)
Click here to see higher resolution photo
Ref - 6590
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - Concrete sleepers brought in by the excavator. (22/01/2021)
Click here to see higher resolution photo
Ref - 6591
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - A couple of walkers crossing the worksight over the upturned concrete sleepers with a slight gap between each to allow excess water to run into the U tubes.
The official footpath should be near the telegraph pole in the background but the route seems to have been diverted officially or unofficially as no gates/stiles exist at that point. (22/01/2021)Click here to see higher resolution photo
Ref - 6630
Photo - Andy Waite
Smiths User Worked Crossing Replacement - The infrastructure team working on replacing Smiths User Worked Crossing (22/01/2021)
Click here to see higher resolution photo
Ref - 6592
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - Most of these U tubes with lids were totally grassed over and have been cleared along with extensive de-weeding in the ballast. The travelling crane jib height warning sign was reinstated as it was found buried in the grass. (25/01/2021)
Click here to see higher resolution photo
Ref - 6609
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - One 120' rail back in. (25/01/2021)
Click here to see higher resolution photo
Ref - 6593
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - The remaining gap was filled with good second hand wood sleepers. (25/01/2021)
Click here to see higher resolution photo
Ref - 6610
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - All sleepers and rails in and jointed up. (26/01/2021)
Click here to see higher resolution photo
Ref - 6594
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - The crossing area has had ballast installed and is being levelled up and packed with the Robel. (26/01/2021)
Click here to see higher resolution photo
Ref - 6595
Photo - Andy Waite
Smiths User Worked Crossing Replacement - The infrastructure team working on replacing Smiths User Worked Crossing (28/01/2021)
Click here to see higher resolution photo
Ref - 6596
Photo - Andy Waite
Smiths User Worked Crossing Replacement - The infrastructure team working on replacing Smiths User Worked Crossing (28/01/2021)
Click here to see higher resolution photo
Ref - 6597
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - View towards Constable Burton old station site with ballast installed, jacked and packed. (29/01/2021)
Click here to see higher resolution photo
Ref - 6611
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - View uphill with new deck in. (29/01/2021)
Click here to see higher resolution photo
Ref - 6598
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - View downhill with the excavator having some mud removed. (29/01/2021)
Click here to see higher resolution photo
Ref - 6612
Photo - Michael Metcalfe
Smiths User Worked Crossing Replacement - Final view towards Finghall Station with the JCB loader bringing in more ballast to finish the job off. Just a bit of tidying up left to do. (29/01/2021)
Click here to see higher resolution photo
Tip - You may find it better to view the pictures in 'full screen' mode - For most browsers F11 will toggle this on and off