Bedale Level Crossing Replacement
by the Infrastructure Group
In January 2013 the railway carried out a complete refurbishment of Bedale Level Crossing. Below you can see a comprehensive photographic record of the work.
Operation of the photo gallery has been altered so that it now also works with touch screen devices. Hover the mouse over a thumbnail to see the full size picture to the right. If you click or tap on the thumbnail then it will cause the selected picture to stay on the right. Select the link under the picture will bring up a higher resolution picture where available.

Photo - Mike Brittlebank
Photo showing the poor state of the decking of Bedale Level Crossing prior to commencement of replacement (03/01/2013)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Photo showing the poor state of the decking of Bedale Level Crossing prior to commencement of replacement (03/01/2013)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Photo showing the poor state of the decking of Bedale Level Crossing prior to commencement of replacement (03/01/2013)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing prior to commencement of replacement (03/01/2013)
Click here to see higher resolution photo
Photo - Mike Brittlebank
The three 60' track Panels for Bedale Level Crossing being built in the yard at Leeming Bar (15/12/2014)
Click here to see higher resolution photo
Photo - Mike Brittlebank
The three 60' track Panels for Bedale Level Crossing being built in the yard at Leeming Bar (15/12/2014)
Click here to see higher resolution photo
Photo - Mike Brittlebank
The three 60' track Panels for Bedale Level Crossing in the yard at Leeming Bar ready for delivery (22/12/2014)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - Removing the old decking and rails (05/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - Removing the old decking and rails (05/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - Removing the old decking and rails (05/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - Temporary Decking down to allow road vehicles to cross (05/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - Digging out the ballast (07/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - The track bed has been dug out and ready for the new ballast (07/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - New ballast is now down and level (10/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - Digging out the track at the station side (10/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - Digging out the track at the station side (10/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - The 130 Tonne Crane preparing for action (12/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - End on to "Salmon" (rail carrying wagon), White material is Geo-textile (12/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - The 1st panel in position (12/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - The 3rd panel in position (12/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - Cutting Rail to length (12/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - The track all reconnected, BIG sigh of relief (12/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - Crossing now ballasted, new crossing decking on the "Salmon" wagon (14/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - The Tamper from VolkerRail, which triple tamped the crossing (14/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - The Tamper from VolkerRail, which triple tamped the crossing (14/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - The Tamper from VolkerRail, which triple tamped the crossing (14/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - The new decking has now been laid (28/01/2015)
Click here to see higher resolution photo
Photo - Mike Brittlebank
Bedale Level Crossing replacement - The gates have now been reinstalled - the crossing is now complete
A job well done (09/02/2015)Click here to see higher resolution photo