Wensleydale Railway - Photo Archive


Harmby Track Relay
(January to March 2022)
From late January through to early March 2022, our Infrastructure Teams relaid about half a mile of track through the cutting at Harmby, a notoriously wet part of the line near to Leyburn with the flat bottomed rail and concrete sleepers that we got from Eggborough Power Station last year.

Ref - 9813
Photo - Unknown Photographer
The tamper from VolkerRail has just arrived and is ready to work on the recently relaid section of line at Harmby, just east of Leyburn. A huge thanks to VolkerRail! (29/03/2022)
Click here to see higher resolution photo
Ref - 9813
Photo - Unknown Photographer
The tamper from VolkerRail has just arrived and is ready to work on the recently relaid section of line at Harmby, just east of Leyburn. A huge thanks to VolkerRail! (29/03/2022)
Click here to see higher resolution photo
Ref - 9529
Photo - P. Garnett
Loco 37250 passing Finghall with a works train moving sleepers and rails to the track relay sites (04/01/2022)
Click here to see higher resolution photo
Ref - 9530
Photo - P. Garnett
A view from the cab of loco 37250 with our road/rail machine in the distance (04/01/2022)
Click here to see higher resolution photo
Ref - 9621
Photo - P. Garnett
Unloading rails from the works train at the works site (04/01/2022)
Click here to see higher resolution photo
Ref - 9531
Photo - P. Garnett
Unloading rail from the works train at the works site (04/01/2022)
Click here to see higher resolution photo
Ref - 9532
Photo - P. Garnett
The works train at Redmire being loaded with rail (04/01/2022)
Click here to see higher resolution photo
Ref - 9533
Photo - P. Garnett
The works train at Leyburn (04/01/2022)
Click here to see higher resolution photo
Ref - 9534
Photo - Alan Graham
A member of the vegetation team takes stock as works train no D37250 pauses at Redmire before taking a new load of sleepers and rails eastwards from Redmire. (12/01/2022)
Click here to see higher resolution photo
Ref - 9535
Photo - Michael Metcalfe
37250 Arriving at Leyburn to pick up some workers for rail/sleeper drop. (12/01/2022)
Click here to see higher resolution photo
Ref - 9536
Photo - Michael Metcalfe
37250 hooked up to wagons ready for loading at Redmire. (12/01/2022)
Click here to see higher resolution photo
Ref - 9537
Photo - Michael Metcalfe
Concrete sleepers been loaded. (12/01/2022)
Click here to see higher resolution photo
Ref - 9538
Photo - Michael Metcalfe
RRV and trailer loaded up with equipment. (12/01/2022)
Click here to see higher resolution photo
Ref - 9539
Photo - Michael Metcalfe
Shark van on Primrose crossing. (12/01/2022)
Click here to see higher resolution photo
Ref - 9540
Photo - Michael Metcalfe
37250 set back getting ready to drop rails at Primrose crossing for a future relay job. (12/01/2022)
Click here to see higher resolution photo
Ref - 9541
Photo - Michael Metcalfe
37250 leaving Leyburn heading for Constable Burton loop at the end of the day. (12/01/2022)
Click here to see higher resolution photo
Ref - 9542
Photo - P. Garnett
Loading sleepers at Redmire, ready to be taken to the works site near Leyburn (14/01/2022)
Click here to see higher resolution photo
Ref - 9622
Photo - P. Garnett
Loading sleepers at Redmire, ready to be taken to the works site near Leyburn (14/01/2022)
Click here to see higher resolution photo
Ref - 9543
Photo - Alan Graham
Works train D37250 waits at Redmire as it pauses to couple with trucks out of sight in this picture taken on Weds 19/01/22. (19/01/2022)
Click here to see higher resolution photo
Ref - 9544
Photo - Toby Albrecht
Toby Albrecht of the vegetation team captured this image of the works train leaving Redmire with a load of fresh rails and sleepers on 19th January 22. (19/01/2022)
Click here to see higher resolution photo
Ref - 9625
Photo - Andy Waite
The track relay site near Harmby, Leyburn - day 1 - In Harmby cutting after the rails have been removed (24/01/2022)
Click here to see higher resolution photo
Ref - 9545
Photo - Andy Waite
The track relay site near Harmby, Leyburn - day 1 - looking west after the the rails and sleepers have been removed (24/01/2022)
Click here to see higher resolution photo
Ref - 9626
Photo - Andy Waite
The track relay site near Harmby, Leyburn - day 1 - looking east (24/01/2022)
Click here to see higher resolution photo
Ref - 9546
Photo - Andy Glendinning
Harmby Cutting. How to dishearten the Leyburn Pway team who spent most of last summer replacing sleepers, oiling fishplates etc to get this track compliant so trains could run again to Leyburn. Someone has now decided this section is to be relaid.
All that effort wasted. (25/01/2022)Click here to see higher resolution photo
Ref - 9547
Photo - P. Garnett
The infrastructure team working at the track relay site near Harmby, Leyburn. Here the rails have been removed, the old sleepers will be next (25/01/2022)
Click here to see higher resolution photo
Ref - 9548
Photo - P. Garnett
The infrastructure team working at the track relay site near Harmby, Leyburn. Here the rails and sleepers have been removed. (25/01/2022)
Click here to see higher resolution photo
Ref - 9549
Photo - P. Garnett
Our road/rail machine in the process of removing the old rails at the relay site near Harmby, Leyburn (25/01/2022)
Click here to see higher resolution photo
Ref - 9550
Photo - Alex Lomax
The infrastructure team continuing working at the track relay site near Harmby, Leyburn. (26/01/2022)
Click here to see higher resolution photo
Ref - 9551
Photo - Alex Lomax
The infrastructure team continuing working at the track relay site near Harmby, Leyburn. (26/01/2022)
Click here to see higher resolution photo
Ref - 9552
Photo - Alex Lomax
The infrastructure team continuing working at the track relay site near Harmby, Leyburn. (26/01/2022)
Click here to see higher resolution photo
Ref - 9553
Photo - Alex Lomax
The infrastructure team continuing working at the track relay site near Harmby, Leyburn. (26/01/2022)
Click here to see higher resolution photo
Ref - 9554
Photo - Alex Lomax
The infrastructure team continuing working at the track relay site near Harmby, Leyburn. (26/01/2022)
Click here to see higher resolution photo
Ref - 9555
Photo - P. Garnett / A. Lomax
The old track and sleepers have now all been removed from the track relay site near Harmby, Leyburn (27/01/2022)
Click here to see higher resolution photo
Ref - 9556
Photo - P. Garnett / A. Lomax
Preparing the track bed for the new sleepers and rails at the the track relay site near Harmby, Leyburn (27/01/2022)
Click here to see higher resolution photo
Ref - 9557
Photo - P. Garnett / A. Lomax
Preparing the track bed for the new sleepers and rails at the the track relay site near Harmby, Leyburn (27/01/2022)
Click here to see higher resolution photo
Ref - 9624
Photo - P. Garnett / A. Lomax
Preparing the track bed for the new sleepers and rails at the the track relay site near Harmby, Leyburn (27/01/2022)
Click here to see higher resolution photo
Ref - 9558
Photo - Michael Metcalfe
Sleepers and tools been delivered to the Harmby Relay worksite. (31/01/2022)
Click here to see higher resolution photo
Ref - 9649
Photo - P. Garnett
The first of the 'new to us' sleepers from Eggborough Power Station being laid at Harmby track relay site near Leyburn (31/01/2022)
Click here to see higher resolution photo
Ref - 9559
Photo - Michael Metcalfe
A rail been moved onto the second panel of track to be installed. (31/01/2022)
Click here to see higher resolution photo
Ref - 9560
Photo - Michael Metcalfe
Excavator moving the other end of the rail into the correct position. (31/01/2022)
Click here to see higher resolution photo
Ref - 9561
Photo - Michael Metcalfe
The rail drill, drilling fish plate holes in the end of a rail. (31/01/2022)
Click here to see higher resolution photo
Ref - 9614
Photo - Michael Metcalfe
A general view of two track panels partly installed. (31/01/2022)
Click here to see higher resolution photo
Ref - 9562
Photo - Michael Metcalfe
The excavator pulling the rail and sleepers into the correction position marked on the ground. (31/01/2022)
Click here to see higher resolution photo
Ref - 9679
Photo - Michael Metcalfe
4 Concrete sleepers been carried by the excavator and spaced out using the Z gauge. (03/02/2022)
Click here to see higher resolution photo
Ref - 9680
Photo - Michael Metcalfe
Clipping the rails to sleepers is a time consuming/repetitive job. (07/02/2022)
Click here to see higher resolution photo
Ref - 9681
Photo - Alex Lomax
The infrastructure team are now roughly one third of the way through the latest relay at Harmby, Leyburn (07/02/2022)
Click here to see higher resolution photo
Ref - 9682
Photo - Alex Lomax
The infrastructure team are now roughly one third of the way through the latest relay at Harmby, Leyburn (07/02/2022)
Click here to see higher resolution photo
Ref - 9683
Photo - Alex Lomax
The infrastructure team are now roughly one third of the way through the latest relay at Harmby, Leyburn (07/02/2022)
Click here to see higher resolution photo
Ref - 9684
Photo - Alex Lomax
The infrastructure team are now roughly one third of the way through the latest relay at Harmby, Leyburn (07/02/2022)
Click here to see higher resolution photo
Ref - 9685
Photo - Alex Lomax
The infrastructure team are now roughly one third of the way through the latest relay at Harmby, Leyburn (07/02/2022)
Click here to see higher resolution photo
Ref - 9686
Photo - Michael Metcalfe
Track bed been dug out under B23 Harmby to allow clearance to the bridge with concrete sleepers and flat bottom rail. (08/02/2022)
Click here to see higher resolution photo
Ref - 9687
Photo - Andy Glendinning
Harmby relay. End of existing track looking east, Harmby Bridge in the background. (11/02/2022)
Click here to see higher resolution photo
Ref - 9688
Photo - Michael Metcalfe
Another day - more clipping in Harmby cutting. (14/02/2022)
Click here to see higher resolution photo
Ref - 9689
Photo - Andy Glendinning
Harmby relay. New track laid through Harmby Cutting and under Harmby Bridge. (22/02/2022)
Click here to see higher resolution photo
Ref - 9690
Photo - Andy Glendinning
Harmby relay. More sleepers laid out ready to receive another 60 foot of rail.
The end of old track shown in the 11th February picture is in the distance at the top of this frame. (22/02/2022)Click here to see higher resolution photo
Ref - 9691
Photo - Unknown Photographer
Our amazing Infrastructure team have battled on with the latest relay at Harmby, Leyburn despite the recent storms and floods.
Unfortunately this has caused a delay to progress and will not now be ready for trains till well into March (26/02/2022)Click here to see higher resolution photo
Ref - 9692
Photo - Unknown Photographer
Our amazing Infrastructure team have battled on with the latest relay at Harmby, Leyburn despite the recent storms and floods.
Unfortunately this has caused a delay to progress and will not now be ready for trains till well into March (26/02/2022)Click here to see higher resolution photo
Ref - 9693
Photo - Unknown Photographer
Our amazing Infrastructure team have battled on with the latest relay at Harmby, Leyburn despite the recent storms and floods.
Unfortunately this has caused a delay to progress and will not now be ready for trains till well into March (26/02/2022)Click here to see higher resolution photo
Ref - 9694
Photo - Unknown Photographer
Our amazing Infrastructure team have battled on with the latest relay at Harmby, Leyburn despite the recent storms and floods.
Unfortunately this has caused a delay to progress and will not now be ready for trains till well into March (26/02/2022)Click here to see higher resolution photo
Ref - 9750
Photo - Unknown Photographer
Our incredible Infrastructure team have endured the worst possible weather over the past couple of weeks to keep the momentum of the track relay at Harmby near Leyburn “on track” (04/03/2022)
Click here to see higher resolution photo
Ref - 9751
Photo - Unknown Photographer
Our incredible Infrastructure team have endured the worst possible weather over the past couple of weeks to keep the momentum of the track relay at Harmby near Leyburn “on track” (04/03/2022)
Click here to see higher resolution photo
Ref - 9804
Photo - Unknown Photographer
Our incredible Infrastructure team have endured the worst possible weather over the past couple of weeks to keep the momentum of the track relay at Harmby near Leyburn “on track” (04/03/2022)
Click here to see higher resolution photo
Ref - 9805
Photo - Unknown Photographer
Our incredible Infrastructure team have endured the worst possible weather over the past couple of weeks to keep the momentum of the track relay at Harmby near Leyburn “on track” (04/03/2022)
Click here to see higher resolution photo
Ref - 9806
Photo - Andy Glendinning
Ballast working through Leyburn for the Harmby relay. (10/03/2022)
Click here to see higher resolution photo
Ref - 9807
Photo - Unknown Photographer
Now that the track has all been laid at the Harmby track relay, the track is being covered with ballast in readiness of the tamper arriving (11/03/2022)
Click here to see higher resolution photo
Ref - 9752
Photo - Unknown Photographer
Now that the track has all been laid at the Harmby track relay, the track is being covered with ballast in readiness of the tamper arriving (11/03/2022)
Click here to see higher resolution photo
Ref - 9753
Photo - Unknown Photographer
Now that the track has all been laid at the Harmby track relay, the track is being covered with ballast in readiness of the tamper arriving (11/03/2022)
Click here to see higher resolution photo
Ref - 9808
Photo - Unknown Photographer
Now that the track has all been laid at the Harmby track relay, the track is being covered with ballast in readiness of the tamper arriving (11/03/2022)
Click here to see higher resolution photo
Ref - 9809
Photo - Andy Glendinning
Another ballast working,the Shark ballast plough prominent. (11/03/2022)
Click here to see higher resolution photo
Ref - 9810
Photo - Andy Glendinning
Tidy up time after the Harmby relay. (21/03/2022)
Click here to see higher resolution photo
Ref - 9811
Photo - GimbalAir
An aerial view of the nearly completed track relay at Harmby. Just needs to be tampered now (26/03/2022)
Click here to see higher resolution photo
Ref - 9812
Photo - GimbalAir
An aerial view of the nearly completed track relay at Harmby. Just needs to be tampered now (26/03/2022)
Click here to see higher resolution photo