Wensleydale Railway - Photo Archive


Leyburn Shawl (Wensley) Track Slew
As part of the 'Return to Redmire' project, the track-bed below Leyburn shawl near Wensley was suffering erosion leading to insufficient ballast support for the track along the embankment edge for around 3/4 mile. The track needs to be moved further away from the edge, using the area that was previously a quarry siding.

Ref - 14725
Photo - Michael Metcalfe
Leyburn Shawl Track Slew - Vegetation needs to be removed prior to digging out at the Leyburn Shawl slew site. Lampitt Rail Services RRV stoking the fire. (05/09/2024)
Click here to see higher resolution photo
Ref - 14725
Photo - Michael Metcalfe
Leyburn Shawl Track Slew - Vegetation needs to be removed prior to digging out at the Leyburn Shawl slew site. Lampitt Rail Services RRV stoking the fire. (05/09/2024)
Click here to see higher resolution photo
Ref - 14789
Photo - David Winpenny
Leyburn Shawl Track Slew - (--/09/2024)
Click here to see higher resolution photo
Ref - 14787
Photo - David Winpenny
Leyburn Shawl Track Slew - A digger digging out the area where the track is being moved to (--/09/2024)
Click here to see higher resolution photo
Ref - 14790
Photo - David Winpenny
Leyburn Shawl Track Slew - Track bed dug out ready to receive ballast (--/09/2024)
Click here to see higher resolution photo
Ref - 14791
Photo - David Winpenny
Leyburn Shawl Track Slew - The track bed being prepared (--/09/2024)
Click here to see higher resolution photo
Ref - 14788
Photo - David Winpenny
Leyburn Shawl Track Slew - Rotten sleepers are also being replaced as necessary (--/09/2024)
Click here to see higher resolution photo
Ref - 14726
Photo - Michael Metcalfe
Leyburn Shawl Track Slew - The slew site is on a mixture of wood and concrete sleepers so the worn out woods have to be replaced with good used sleepers. The RRV does the hard by removing and replacing the wood sleepers where required. WR Volunteers screwing replacement sleepers down. (12/09/2024)
Click here to see higher resolution photo
Ref - 14727
Photo - Michael Metcalfe
Leyburn Shawl Track Slew - The track bed has been dug out at this section ready for ballast and eventually the track slew. (12/09/2024)
Click here to see higher resolution photo
Ref - 14728
Photo - Michael Metcalfe
Leyburn Shawl Track Slew - Hired in excavator clearing the track bed. (12/09/2024)
Click here to see higher resolution photo
Ref - 14735
Photo - Andy Glendinning
Leyburn Shawl Track Slew - It's a lot easier removing sleepers with a big machine with a grab rather than by hand. (16/09/2024)
Click here to see higher resolution photo
Ref - 14736
Photo - Andy Glendinning
Leyburn Shawl Track Slew - Geotextile down and first ballast drop to form the bed to move the track across onto. (19/09/2024)
Click here to see higher resolution photo
Ref - 14779
Photo - Alex Lomax
Leyburn Shawl Track Slew - A view from the digger driver's seat (--/09/2024)
Click here to see higher resolution photo
Ref - 14780
Photo - Alex Lomax
Leyburn Shawl Track Slew - The digger smoothing out ballast (--/09/2024)
Click here to see higher resolution photo
Ref - 14781
Photo - Alex Lomax
Leyburn Shawl Track Slew - The digger smoothing out ballast onto geotextile (--/09/2024)
Click here to see higher resolution photo
Ref - 14782
Photo - Alex Lomax
Leyburn Shawl Track Slew - The new trackbed ready for some ballast (--/09/2024)
Click here to see higher resolution photo
Ref - 14783
Photo - Alex Lomax
Leyburn Shawl Track Slew - Work in progress (--/09/2024)
Click here to see higher resolution photo
Ref - 14784
Photo - Alex Lomax
Leyburn Shawl Track Slew - Work in progress (--/09/2024)
Click here to see higher resolution photo
Ref - 14785
Photo - Alex Lomax
Leyburn Shawl Track Slew - Some ballast has been laid where the track is being moved to (--/09/2024)
Click here to see higher resolution photo
Ref - 14786
Photo - Alex Lomax
Leyburn Shawl Track Slew - Some ballast has been laid where the track is being moved to (--/09/2024)
Click here to see higher resolution photo
Ref - 14932
Photo - Alex Lomax
Leyburn Shawl Track Slew - Work is continuing (04/10/2024)
Click here to see higher resolution photo
Ref - 14933
Photo - Alex Lomax
Leyburn Shawl Track Slew - Work is continuing (04/10/2024)
Click here to see higher resolution photo
Ref - 14934
Photo - Alex Lomax
Leyburn Shawl Track Slew - Work is continuing (04/10/2024)
Click here to see higher resolution photo
Ref - 14935
Photo - Alex Lomax
Leyburn Shawl Track Slew - Work is continuing (04/10/2024)
Click here to see higher resolution photo
Ref - 14936
Photo - Alex Lomax
Leyburn Shawl Track Slew - Work is continuing (04/10/2024)
Click here to see higher resolution photo
Ref - 14937
Photo - Alex Lomax
Leyburn Shawl Track Slew - Work is continuing (04/10/2024)
Click here to see higher resolution photo
Ref - 14938
Photo - Alex Lomax
Leyburn Shawl Track Slew - Work is now complete (25/10/2024)
Click here to see higher resolution photo
Ref - 14939
Photo - Alex Lomax
Leyburn Shawl Track Slew - Work is now complete (25/10/2024)
Click here to see higher resolution photo
Ref - 14940
Photo - Alex Lomax
Leyburn Shawl Track Slew - Work is now complete (25/10/2024)
Click here to see higher resolution photo
Ref - 14941
Photo - Alex Lomax
Leyburn Shawl Track Slew - Work is now complete (25/10/2024)
Click here to see higher resolution photo
Ref - 14942
Photo - Alex Lomax
Leyburn Shawl Track Slew - Work is now complete (25/10/2024)
Click here to see higher resolution photo
Ref - 14943
Photo - Alex Lomax
Leyburn Shawl Track Slew - Work is now complete (25/10/2024)
Click here to see higher resolution photo