Wensleydale Railway - Photo Archive


Redmire Mini Track Replacement
by the Infrastructure Group
In September 2018 the railway carried out a mini track replacement at Redmire to get rid of a bad section of track. Below you can see a comprehensive photographic record of the work.

Photo - Ian Yale
(looking towards Leyburn) at the worksite of the Redmire mini track renewal showing the extent of the vegetation encroachment lineside on the left of the image before Andy Chapman of the Infrastructure team was let loose with his chainsaw (10/09/2018)
Click here to see higher resolution photo
Photo - Ian Yale
(looking towards Leyburn) at the worksite of the Redmire mini track renewal showing the extent of the vegetation encroachment lineside on the left of the image before Andy Chapman of the Infrastructure team was let loose with his chainsaw (10/09/2018)
Click here to see higher resolution photo
Photo - Ian Yale
The Infrastructure team clearing vegetation and disposing of brash on bonfire at the worksite of the Redmire mini track renewal (10/09/2018)
Click here to see higher resolution photo
Photo - Ian Yale
The Infrastructure Team tree felling at the worksite of the Redmire mini track renewal (10/09/2018)
Click here to see higher resolution photo
Photo - Ian Yale
Showing extent of clearance achieved at the worksite of the Redmire mini track renewal by the Infrastructure Team (finding in the process the remains of a buffer stop [to be removed for scrap during the track renewal] and the rails and concrete base of a Wickham trolley hut). (10/09/2018)
Click here to see higher resolution photo
Photo - Ian Yale
The extent of vegetation clearance at the worksite of the Redmire mini track renewal by the Infrastructure Team to allow JCB room to manoeuvre (10/09/2018)
Click here to see higher resolution photo
Photo - Ian Yale
A reference 'before' image showing the site of the track requiring complete renewal at Redmire with the four lengths of flat bottom rail. (10/09/2018)
Click here to see higher resolution photo
Photo - Ian Yale
The Infrastructure team rolling the flat bottom rails from the cess at Redmire into the four foot (10/09/2018)
Click here to see higher resolution photo
Photo - Ian Yale
The Infrastructure team using the ironmen to lift and then move the rails the short distance from the dairy at Redmire to the worksite. (10/09/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
The works train rests overnight at Leyburn while heading to Redmire for the track relay the next day. (12/09/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
An early morning visitor takes the sun on one of the gate posts at Wensley while awaiting the works train. (13/09/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
The works train approaches Wensley Crossing. (13/09/2018)
Click here to see higher resolution photo
Photo - Michael Metcalfe
Works train with 20166 at Redmire during mini 120' relay of track. (13/09/2018)
Click here to see higher resolution photo
Photo - Michael Metcalfe
Digger loaded onto Flatrol for short hop past Bridge 32 and a set of points. (13/09/2018)
Click here to see higher resolution photo
Photo - Michael Metcalfe
44 concrete sleepers were unloaded for the relay. (13/09/2018)
Click here to see higher resolution photo
Photo - Michael Metcalfe
Old track removed and now digging out the old sleepers and ballast to the correct depth. (13/09/2018)
Click here to see higher resolution photo
Photo - Michael Metcalfe
The digger and operator Jim in close up. (13/09/2018)
Click here to see higher resolution photo
Photo - Infrastructure Team
The Redmire mini track renewal - The area dug out by the Infrastructure team ready for installation (13/09/2018)
Click here to see higher resolution photo
Photo - Michael Metcalfe
Dogfish on rear of works train which will be loaded with ballast the next day. (13/09/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Redmire Relay Day 2. Setting out the string line to square up the first panel of sleepers. (14/09/2018)
Click here to see higher resolution photo
Photo - Infrastructure Team
The Redmire mini track renewal - New concrete sleepers laid and lined up ready for the rails (14/09/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Redmire Relay Day 2. Rail in, clipped up, fishplated and ready for ballast. (14/09/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Redmire Relay Day 2. Setting back to drop ballast. (14/09/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Redmire Relay Day 2. Ballast dropped, just lots of machine and hand shovelling to get it in the right places. (14/09/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Redmire Relay Day 2. End of the day. (14/09/2018)
Click here to see higher resolution photo
Photo - Infrastructure Team
The Redmire mini track renewal - The job complete. Just needs a visit from the tamper now, but will be OK for 5mph in the interim. (14/09/2018)
Click here to see higher resolution photo
Photo - Infrastructure Team
The Redmire mini track renewal - The section has now been tamped and is looking good (19/09/2018)
Click here to see higher resolution photo
Tip - You may find it better to view the pictures in 'full screen' mode - For most browsers F11 will toggle this on and off
© 2021 Wensleydale Railway