Leeming Bar Shed
Construction of the new shed at Leeming Bar started in December 2017 with the foundations.
In January 2018 the shed itself started to go up. Completion of the project was in June 2018 with the completion of the track and points into the shed. Here are some photos to show it's construction.

Photo - Andy Glendinning
New shed area at Leeming Bar, showing the preparatory work for the foundations. (12/12/2017)
Click here to see higher resolution photo
Photo - Andy Glendinning
New shed area at Leeming Bar, showing the preparatory work for the foundations. (12/12/2017)
Click here to see higher resolution photo
Photo - Andy Glendinning
Leeming Bar new shed, one of the foundation pits. (12/12/2017)
Click here to see higher resolution photo
Photo - Andy Glendinning
Concrete mixed to order for the foundations for the new Leeming Bar shed. (12/12/2017)
Click here to see higher resolution photo
Photo - Andy Glendinning
No shovelling or barrows, the concrete goes straight in the hole for the new Leeming Bar shed foundations. (12/12/2017)
Click here to see higher resolution photo
Photo - Andy Glendinning
Work continues on the new Leeming Bar shed foundations. (12/12/2017)
Click here to see higher resolution photo
Photo - John Tong
The new shed at Leeming Bar - Third Frame is now up. (10/01/2018)
Click here to see higher resolution photo
Photo - John Tong
The new shed at Leeming Bar - Fourth Frame is erected (10/01/2018)
Click here to see higher resolution photo
Photo - John Tong
The new shed at Leeming Bar - The fifth frame is up (10/01/2018)
Click here to see higher resolution photo
Photo - John Tong
The new shed at Leeming Bar - Sixth frame boing positioned (10/01/2018)
Click here to see higher resolution photo
Photo - John Tong
The new shed at Leeming Bar - The sixth frame being secured (10/01/2018)
Click here to see higher resolution photo
Photo - Timothy Edwards
Leeming Bar Shed - The framework is now complete (16/01/2018)
Click here to see higher resolution photo
Photo - Timothy Edwards
Leeming Bar Shed - The framework is now complete (16/01/2018)
Click here to see higher resolution photo
Photo - Timothy Edwards
Leeming Bar Shed - The framework is now complete (16/01/2018)
Click here to see higher resolution photo
Photo - John Tong
Leeming Bar Shed - all 9 Frames of the shed complete (17/01/2018)
Click here to see higher resolution photo
Photo - John Tong
Leeming Bar Shed - safety scaffolding erected on one side on top prior to the roof being covered. (17/01/2018)
Click here to see higher resolution photo
Photo - Timothy Edwards
Leeming Bar Shed - The roof is now going on. (23/01/2018)
Click here to see higher resolution photo
Photo - Timothy Edwards
Leeming Bar Shed - The roof is now going on. (23/01/2018)
Click here to see higher resolution photo
Photo - Timothy Edwards
Leeming Bar Shed - The roof is now going on. (23/01/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
The New Shed at Leeming Bar. Framework almost complete. (13/01/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
The New Shed at Leeming Bar. Safety rail and netting going up to allow the roof panels to be fixed. (17/01/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
The New Shed at Leeming Bar. South side cladding going on. (29/01/2018)
Click here to see higher resolution photo
Photo - Timothy Edwards
Leeming Bar Shed - The north side still need to be done (30/01/2018)
Click here to see higher resolution photo
Photo - Timothy Edwards
Leeming Bar Shed - Start of the north side of the shed (30/01/2018)
Click here to see higher resolution photo
Photo - Timothy Edwards
Leeming Bar Shed - West end still to go on (30/01/2018)
Click here to see higher resolution photo
Photo - Timothy Edwards
Leeming Bar Shed - The south side is complete (30/01/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
The New Shed at Leeming Bar. South cladding and end cladding complete (apart from cutting the square panels to the roof line on the end). (30/01/2018)
Click here to see higher resolution photo
Photo - Wensleydale Railway
The first train in the new Leeming Bar shed (--/02/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
The New Shed at Leeming Bar. The second track being laid. (21/02/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
The New Shed at Leeming Bar. The second track being laid. (21/02/2018)
Click here to see higher resolution photo
Photo - Alex Dudiak
The shed is essentially complete, with the end roller doors in place and guttering added. (24/02/2018)
Click here to see higher resolution photo
Photo - Alex Dudiak
The second track is now laid and being compacted ready for the concrete floor to be poured (24/02/2018)
Click here to see higher resolution photo
Photo - Alex Dudiak
View from inside the shed, showing the amount of light and general airiness of the building (24/02/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
The new Leeming Bar shed. Jennifer's smokebox. (23/03/2018)
Click here to see higher resolution photo
Photo - John Tong
Steam locomotive 'Jennifer' in Leeming Bar shed. Note that the shed floor has now been concreted. (21/03/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
The new Leeming Bar shed. The lady 'Jennifer' herself. (23/03/2018)
Click here to see higher resolution photo
Photo - John Tong
Steam locomotive 'Jennifer' in Leeming Bar shed. Note that the shed floor has now been concreted. (21/03/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
The New Shed. The LNWR Directors Saloon receives some TLC. (23/03/2018)
Click here to see higher resolution photo
Photo - Alastair Connell
With the aid of a JCB, the Infrastructure Team make a start at putting a point and track to the south road in the new shed (27/04/2018)
Click here to see higher resolution photo
Photo - Alastair Connell
The infrastructure Team working on connecting in the south road of the new shed (28/04/2018)
Click here to see higher resolution photo
Photo - Alastair Connell
The infrastructure Team working on connecting in the south road of the new shed (28/04/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Track being laid from the second road of The New Shed with steam loco Jennifer. (28/04/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Points going in for the second road into the new shed. (28/04/2018)
Click here to see higher resolution photo
Photo - WR Infrastructure
The Infrastructure team working on the new point for the south road of the new shed (05/05/2018)
Click here to see higher resolution photo
Photo - WR Infrastructure
The nose of the new point for the shed south road is now looking good (05/05/2018)
Click here to see higher resolution photo
Photo - WR Infrastructure
The nose of the new point for the shed south road is now looking good (05/05/2018)
Click here to see higher resolution photo
Photo - WR Infrastructure
Andy Waite helps install the check rail on the new points for the south road of the new shed (23/05/2018)
Click here to see higher resolution photo
Photo - WR Infrastructure
A work in progress on the points for the south road of the new shed (23/05/2018)
Click here to see higher resolution photo
Photo - WR Infrastructure
A work in progress on the points for the south road of the new shed (23/05/2018)
Click here to see higher resolution photo
Photo - WR Infrastructure
Hardwood timbers laid out for the new switches in the yard for the points for the south road of the new shed (26/05/2018)
Click here to see higher resolution photo
Photo - WR Infrastructure
At the end of the day the state of play for the new points for the south road of the new shed (26/05/2018)
Click here to see higher resolution photo
Photo - WR Infrastructure
First switch put-in. Starting to look like points now for the Leeming shed south road (30/05/2018)
Click here to see higher resolution photo
Photo - Alastair Connell
The Infrastructure Team working on the last section of the point at Leeming Bar yard for the second track into the new shed (16/06/2018)
Click here to see higher resolution photo
Photo - Alastair Connell
The Infrastructure Team working on the last section of the point at Leeming Bar yard for the second track into the new shed (16/06/2018)
Click here to see higher resolution photo
Photo - Andy Chapman
The finished point in Leeming Bar yard leading to the second road into the new shed. The shed and associated work has now been completed and the shed can now be used fully for its maintenance and other purposes (26/06/2018)
Click here to see higher resolution photo
Photo - Ian Yale
Both roads in the new Leeming Bar shed are now in use (26/06/2018)
Click here to see higher resolution photo
Photo - Ian Yale
Both roads in the new Leeming Bar shed are now in use (26/06/2018)
Click here to see higher resolution photo
Photo - Ian Yale
Both roads in the new Leeming Bar shed are now in use (26/06/2018)
Click here to see higher resolution photo
Photo - Timothy Edwards
Merchant Navy Class Locomotive 'British India Line' in the shed at Leeming Bar (23/07/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Result. NELPG's J27 65894 simmers in The New Shed at Leeming Bar at the start of its season. (28/07/2018)
Click here to see higher resolution photo