Wensleydale Railway - Photo Archive


Leyburn Loop - 1
Here are some photos to show the progress the construction of the loop and water tower at Leyburn

Photo - Andy Glendinning
Continuing works at Leyburn in preparation for the new passing loop. (26/12/2017)
Click here to see higher resolution photo
Photo - Andy Glendinning
Continuing works at Leyburn in preparation for the new passing loop. (26/12/2017)
Click here to see higher resolution photo
Photo - Andy Glendinning
New pipe in place from the new water tank position to feed the down platform at Leyburn. (26/12/2017)
Click here to see higher resolution photo
Photo - David Walker
Leyburn Loop Work - The blue pipe will connect the water tower to the water crane to be located at the end of the existing platform. The water tower will be opposite and located on a shelf in the north cess (to the right in this photo). Creating the shelf was particularly challenging as the rock is a very hard sandstone. Photos show Colin Brown (left), Stigo Parker (digger) and David Harrison (centre). (--/12/2017)
Click here to see higher resolution photo
Photo - David Walker
Leyburn Loop Work - The blue pipe will connect the water tower to the water crane to be located at the end of the existing platform. The water tower will be opposite and located on a shelf in the north cess (to the right in this photo). Creating the shelf was particularly challenging as the rock is a very hard sandstone. Photos show Colin Brown (left), Stigo Parker (digger) and David Harrison (centre). (--/12/2017)
Click here to see higher resolution photo
Photo - David Walker
Leyburn Loop Work - The blue pipe will connect the water tower to the water crane to be located at the end of the existing platform. The water tower will be opposite and located on a shelf in the north cess (to the right in this photo). Creating the shelf was particularly challenging as the rock is a very hard sandstone. Photos show Colin Brown (left), Stigo Parker (digger) and David Harrison (centre). (--/12/2017)
Click here to see higher resolution photo
Photo - David Walker
A pile of ballast at Leyburn ready for use. (--/12/2017)
Click here to see higher resolution photo
Photo - Andy Glendinning
Preparatory works for the new loop at Leyburn. (03/01/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Preparatory works for the new loop at Leyburn. (03/01/2018)
Click here to see higher resolution photo
Photo - David Walker
Preparing the ground for the new passing loop at Leyburn (03/01/2018)
Click here to see higher resolution photo
Photo - David Walker
Preparing the ground for the new passing loop at Leyburn (04/01/2018)
Click here to see higher resolution photo
Photo - David Walker
Preparing the ground for the new passing loop at Leyburn (04/01/2018)
Click here to see higher resolution photo
Photo - David Walker
Preparing the ground for the new passing loop at Leyburn (04/01/2018)
Click here to see higher resolution photo
Photo - David Walker
Preparing the ground for the new passing loop at Leyburn (04/01/2018)
Click here to see higher resolution photo
Photo - David Walker
A works train in Leyburn Station (04/01/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Argill Farm Relay Week One. First panels going into the loop at Leyburn. (12/01/2018)
Click here to see higher resolution photo
Photo - Andy Waite
Leyburn Loop - Track panels from Argill Farm track relaying project are being reused for the Leyburn loop (12/01/2018)
Click here to see higher resolution photo
Photo - Andy Waite
Leyburn Loop - Track panels from Argill Farm track relaying project are being reused for the Leyburn loop (12/01/2018)
Click here to see higher resolution photo
Photo - Andy Waite
Leyburn Loop - Track panels from Argill Farm track relaying project are being reused for the Leyburn loop (12/01/2018)
Click here to see higher resolution photo
Photo - Andy Waite
Leyburn Loop - Track panels from Argill Farm track relaying project are being reused for the Leyburn loop (12/01/2018)
Click here to see higher resolution photo
Photo - Andy Waite
Leyburn Loop - Track panels from Argill Farm track relaying project are being reused for the Leyburn loop (12/01/2018)
Click here to see higher resolution photo
Photo - Andy Waite
Leyburn Loop - Track panels from Argill Farm track relaying project are being reused for the Leyburn loop (12/01/2018)
Click here to see higher resolution photo
Photo - Andy Waite
Leyburn Loop - Track panels from Argill Farm track relaying project are being reused for the Leyburn loop (12/01/2018)
Click here to see higher resolution photo
Photo - Andy Waite
Leyburn Loop - Track panels from Argill Farm track relaying project are being reused for the Leyburn loop (12/01/2018)
Click here to see higher resolution photo
Photo - Andy Waite
Leyburn Loop - Track panels from Argill Farm track relaying project are being reused for the Leyburn loop (12/01/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Leyburn. Track panels from Argill Farm laid out to form the new loop line. (10/02/2018)
Click here to see higher resolution photo
Photo - Andy Waite
The day started for the Infrastructure Team at Leyburn Station dismantling 1 x 30ft track panel in order to make a clear access to the work site on the North side of loop. Hopefully this will make things safer and easier for all working in this area (17/02/2018)
Click here to see higher resolution photo
Photo - Alex Dudiak
Infrastructure team working hard on the alignment of the track panels recovered from Argill which will form the new loop at Leyburn. (24/02/2018)
Click here to see higher resolution photo
Photo - Alex Dudiak
Each track panel needs to be aligned and joined to the previous panel, to make up the loop at Leyburn (24/02/2018)
Click here to see higher resolution photo
Photo - Alex Dudiak
The remaining panels still to be assembled into the loop line at Leyburn (24/02/2018)
Click here to see higher resolution photo
Photo - Alex Dudiak
Its amazing what can be achieved with a few simple tools and hard work. The new loop being formed at Leyburn (24/02/2018)
Click here to see higher resolution photo
Photo - Alex Dudiak
The view towards Redmire at Leyburn. The loop will continue under the bridge where the track will be slewed and a new point installed (24/02/2018)
Click here to see higher resolution photo
Photo - Alex Dudiak
Progress is rapid and within 20 minutes of work a new panel has been attached and aligned for the new Leyburn loop. (24/02/2018)
Click here to see higher resolution photo
Photo - Alastair Connell
A few lengths of track at the eastern end of Leyburn loop have now been aligned into position (24/02/2018)
Click here to see higher resolution photo
Photo - Alastair Connell
A few lengths of track at the eastern end of Leyburn loop have now been aligned into position (24/02/2018)
Click here to see higher resolution photo
Photo - Alastair Connell
The infrastructure team busy working on the track panels to form the Leyburn loop (24/02/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Leyburn West ex signal box base / St Matthew's Well. (10/03/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Leyburn. The Leeming Saturday Infrastructure Gang continue to re-sleeper and join up panels to form the new loop. (10/03/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Leyburn. Concrete pads to support the water tower. (10/03/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Leyburn. New steelwork for the water tower. (10/03/2018)
Click here to see higher resolution photo
Photo - Alastair Connell
More sections of the loop at Leyburn have had sleepers replaced, track aligned and connected (10/03/2018)
Click here to see higher resolution photo
Photo - Alastair Connell
More sections of the loop at Leyburn have had sleepers replaced, track aligned and connected (10/03/2018)
Click here to see higher resolution photo
Photo - Alastair Connell
Andy Chapman of the Infrastructure Team drilling holes in the sleepers at the new west points at Leyburn (10/03/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Leyburn. Steelwork for the new water tower being transported from Peter Black's Crossing to site. (14/03/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Leyburn. First train into the new loop sets gingerly back to unload sleepers. (16/03/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
D9523 with the works train just into the new loop at Leyburn. (16/03/2018)
Click here to see higher resolution photo
Photo - Alastair Connell
A class 14 loco D9523 backing a works train onto the new loop at Leyburn (16/03/2018)
Click here to see higher resolution photo
Photo - Alastair Connell
A class 14 loco backing a works train onto the new loop at Leyburn (16/03/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Leyburn. New water tower base partially erected. (19/03/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Leyburn. The tank in place 'just' the pipework to go. (21/03/2018)
Click here to see higher resolution photo
Photo - Andy Waite
The new water tower at Leyburn is nearing completion (21/03/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Leyburn. New water tower ready to go. (31/03/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Leyburn. Temporary water crane. (31/03/2018)
Click here to see higher resolution photo
Photo - Andy Glendinning
Leyburn. Further re-sleepering and joining track panels in the loop,ballasting and packing still to go. (31/03/2018)
Click here to see higher resolution photo
Photo - Andy Chapman
Work by the Infrastructure Team on connecting up the track panels to create the loop at Leyburn continues (07/04/2018)
Click here to see higher resolution photo
Tip - You may find it better to view the pictures in 'full screen' mode - For most browsers F11 will toggle this on and off
© 2021 Wensleydale Railway