Wensleydale Railway - Photo Archive


Leyburn Loop (3)
Construction of the loop - 2018
Here are a second page of photos to show the progress the construction of the loop and water tower at Leyburn

Ref - 3428
Photo - Michael Metcalfe
Todays task by the Leyburn team was to move 3 point sub assemblies from Peter Blacks UWC (User Worked Crossing) to under bridge 25 where the new Leyburn west points are to be installed was a big learning curve. Here the Ironman frames to be used in the task are receiving some maintenance as they were last used many years ago. (16/04/2018)
Click here to see higher resolution photo
Ref - 3428
Photo - Michael Metcalfe
Todays task by the Leyburn team was to move 3 point sub assemblies from Peter Blacks UWC (User Worked Crossing) to under bridge 25 where the new Leyburn west points are to be installed was a big learning curve. Here the Ironman frames to be used in the task are receiving some maintenance as they were last used many years ago. (16/04/2018)
Click here to see higher resolution photo
Ref - 3449
Photo - Andy Glendinning
One of the switches (18 metres long, 2.4 tonnes) for Leyburn West points was delivered the wrong way round. Some muscle, chopping down of vegetation and the slight easing of a wire fence and notice pole turned it through 180 degrees. (16/04/2018)
Click here to see higher resolution photo
Ref - 3450
Photo - Michael Metcalfe
Leyburn West Point - The first point assembly was in the four foot but 180' wrong way round so a pivot point was created and then spun round but a fence, bushes, and a sign meant it wasn't straight forward. (16/04/2018)
Click here to see higher resolution photo
Ref - 3451
Photo - Michael Metcalfe
Leyburn West Point - Now correct way round and supported on 3 trolleys but the first point assembly was a bit too rigid for the curves and was near to a derailment issue. (16/04/2018)
Click here to see higher resolution photo
Ref - 3429
Photo - Michael Metcalfe
Leyburn West Point - Barring the first point assembly over to the outside of the formation. (16/04/2018)
Click here to see higher resolution photo
Ref - 3430
Photo - Michael Metcalfe
Leyburn West Point - Final adjustment of the position of the first point assembly using the Ironman frame. (16/04/2018)
Click here to see higher resolution photo
Ref - 3432
Photo - Andy Glendinning
With the use of trolleys and an Ironman the second switch was moved to Leyburn West. (16/04/2018)
Click here to see higher resolution photo
Ref - 3452
Photo - Michael Metcalfe
Leyburn West Point - The second point sub assembly with an Ironman frame in the middle and trolleys swapped round and went through the curves no problem. (16/04/2018)
Click here to see higher resolution photo
Ref - 3431
Photo - Michael Metcalfe
Leyburn West Point - Barring the point assembly over towards the wall. (16/04/2018)
Click here to see higher resolution photo
Ref - 3453
Photo - Michael Metcalfe
Leyburn West Point - The third sub assembly on trolley's and Ironman under bridge 25 at Leyburn. (16/04/2018)
Click here to see higher resolution photo
Ref - 3454
Photo - Michael Metcalfe
Leyburn West Point - All 3 point assemblies under bridge 25 outside the lined out area ready for installation later in the year. (16/04/2018)
Click here to see higher resolution photo
Ref - 3433
Photo - Andy Glendinning
All components safely delivered under the bridge to form Leyburn West points. (16/04/2018)
Click here to see higher resolution photo
Ref - 3455
Photo - Andy Glendinning
The water tower, Leyburn complete with new coat of paint. (28/04/2018)
Click here to see higher resolution photo
Ref - 3456
Photo - Andy Glendinning
The new water crane at Leyburn. (28/04/2018)
Click here to see higher resolution photo
Ref - 3734
Photo - Andy Glendinning
Gently setting back into the unballasted loop at Leyburn to drop ballast. (27/07/2018)
Click here to see higher resolution photo
Ref - 3735
Photo - Andy Glendinning
Steady as she goes. (27/07/2018)
Click here to see higher resolution photo
Ref - 3745
Photo - Alastair Connell
The works train laying ballast in the new Leyburn loop (27/07/2018)
Click here to see higher resolution photo
Ref - 3746
Photo - Alastair Connell
The works train laying ballast in the new Leyburn loop (27/07/2018)
Click here to see higher resolution photo
Ref - 3736
Photo - Andy Glendinning
Ready for the tamper. (27/07/2018)
Click here to see higher resolution photo
Ref - 3737
Photo - Andy Glendinning
Ballast dropping. (27/07/2018)
Click here to see higher resolution photo
Ref - 3943
Photo - Andy Glendinning
VolkerRail tamper DR75405 arrives at Leyburn. Note the state of the untamped loop on the left. (18/09/2018)
Click here to see higher resolution photo
Ref - 3931
Photo - Infrastructure Team
A view of the new Leyburn loop from the cab of the tamper (18/09/2018)
Click here to see higher resolution photo
Ref - 3944
Photo - Kev Burnitt
The Volker rail tamper DR75405 tamping on the section of the new loop at Leyburn which has been laid so far. (18/09/2018)
Click here to see higher resolution photo
Ref - 3945
Photo - Michael Metcalfe
The business end of the tamper. Tamping was done in manual mode with every sleeper getting an adjustment by the operator. (18/09/2018)
Click here to see higher resolution photo
Ref - 3946
Photo - Michael Metcalfe
No 2 end of Volker rail tamper DR75405 progressing along the loop on the first run. (18/09/2018)
Click here to see higher resolution photo
Ref - 3947
Photo - Andy Glendinning
Don't believe everything you see on Facebook. THIS is probably the first time two trains have passed at Leyburn since the signalbox closed in 1982. (18/09/2018)
Click here to see higher resolution photo
Ref - 3928
Photo - Michael Metcalfe
Bubble car 121032 arriving at Leyburn station for the 13.20 to Redmire with the Volker rail tamper in the background. (18/09/2018)
Click here to see higher resolution photo
Ref - 3927
Photo - Michael Metcalfe
Volker rail tamper DR75405 outside Chesnutt Cottage at Leyburn station tamping the loop that has been laid so far. (18/09/2018)
Click here to see higher resolution photo
Ref - 3948
Photo - Kev Burnitt
Volker rail tamper DR75405 tamping on the section of the new loop at Leyburn which has been laid so far. (18/09/2018)
Click here to see higher resolution photo
Ref - 3949
Photo - Kev Burnitt
The Volker rail tamper DR75405 tamping on the new loop at Leyburn. It is only doing part of the loop as the loop is not yet complete. (18/09/2018)
Click here to see higher resolution photo
Ref - 3950
Photo - Kev Burnitt
Some hand tamping being done by the Infrastructure Team on the new loop at Leyburn (18/09/2018)
Click here to see higher resolution photo
Ref - 3951
Photo - Andy Glendinning
The Leyburn loop is looking much better now after the tamper has done its job. (18/09/2018)
Click here to see higher resolution photo
Ref - 3929
Photo - Kev Burnitt
Staff on the Volker rail tamper DR75405 at Leyburn (18/09/2018)
Click here to see higher resolution photo
Ref - 3930
Photo - Kev Burnitt
Staff on the Volker rail tamper DR75405 at Leyburn (18/09/2018)
Click here to see higher resolution photo
Ref - 3952
Photo - Infrastructure Team
The Leyburn loop after the visit from the tamper. It's looking much straighter now. (18/09/2018)
Click here to see higher resolution photo
Ref - 4198
Photo - Andy Glendinning
Leyburn West points. New flat bottom rail replaces old bullhead rail between the existing platform flat bottom track and the new points. Time to go home. (14/12/2018)
Click here to see higher resolution photo